Scope of Work
- Site grading and embankment formation including sub- grade and granular sub-base layers for the formation of runway, apron and taxiway.
- Construction of apron extension, taxiway extension, rapid exit ways, main access road and miscellaneous internal roads.
- Embankment formation including sub- grade and granular sub-base and WMM layers for the construction of trumpet interchange connecting NH-7.
- Cutting/excavation of soil in the designated areas to the required level and contours, subsequently obtaining a smooth surface using motor graders and finally using a vibratory compactor to obtain a stable surface.
View all projects
Our Achievements
- Highest quantity of embankment formation in a single month. (Feb-06)-3,49,000 cum
- Highest quantity of sub-grade formation in a single month (May-06)-40,900 cum
- Highest quantity of granular sub-base in a single month (July-06)-52,420 cum.